Detail Mechanical Design for 2Nos. Pig Launcher, 2Nos. Pig Receiver, & 1Nos. Closed Drain.

Project Details

Title: Detail Mechanical Design for 2Nos. Pig Launcher, 2Nos. Pig Receiver, & 1Nos. Closed Drain.

Client: Aveon Offshore Limited / Seflam SGL / Shell Petroleum Development Company SPDC

Location: Eastern Niger Delta, Nigeria

Date: 2024

description

SPDC JV with Shell as operator of OMLs 16, 17, 21, 22, 27 and 28 on behalf of the joint venture partners, embarked on the Gbaran Phase 3B – Uzu with CPF Upgrade project which aims to develop 815Bscf (UR) of gas and 11.5MMbbls (UR) of oil & condensate to meet SPDC’s commitment to sustain NLNG gas supply obligation and grow oil production. The project scope includes infill drilling involving 5 NAG wells and 1 oil well, flowlines, test line and a NAG bulk line from the Uzu field to the Gbaran CPF. 

The facility upgrade scope at the Gbaran Central Processing Facility include debottlenecking of the existing 2 dehydration trains to accommodate additional 200MMscfd from the EPC for Gbaran Phase 3b – UZU with CPF Upgrade Project. All six wells to be drilled as part of this development will be from two existing locations – Zarama 15 and Zarama 08-11 NAG well locations.

Detail Mechanical Design & AFC Drawings for 2Nos. Pig Launcher (ZARAMA 1 & 2), 2Nos. Pig Receiver (GBARAN & ZARAMA 1), & 1Nos. Closed Drain (ZARAMA2)

  1. The following deliverables were developed for equipment tags ZRMS2-V-6701, ZRMS1-A-1001, ZRMS1-A-1003, ZRMS2-A-1001, & GBRG1-A-1040ASME VII Div. 1 & B31.8 Design Calculation 
  2. Finite Element Analysis FEA
  3. Ceasar II Stress Analysis
  4. General Arrangement Drawing
  5. Body Details Drawing
  6. Dished Ends Detailed Drawings
  7. Nozzle Assembly Detailed Drawings
  8. Manhole Assembly Detailed Drawings
  9. Internals Support Detailed Drawings
  10. External Attachments Detailed Drawing
  11. Weld Identification Numbering Drawing
  12. Nameplate Detailed Drawings (Including Bracket)
  13. Material Take Off (MTO)